192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 1300 $8.00 $47.65 $10400.00 01-14-1993 11-169474 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 15800 $10.15 $60.46 $160370.00 01-14-1993 11-189154 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 03 2380 $45.00 $268.04 $107100.00 01-20-1993 03-315504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 240 $60.00 $357.39 $14400.00 01-26-1993 04-121384 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 42600 $8.00 $47.65 $340800.00 01-28-1993 07-110274 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 1050 $70.00 $416.96 $73500.00 01-28-1993 07-111714 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 570 $27.00 $160.83 $15390.00 01-28-1993 11-010644 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 1970 $70.00 $416.96 $137900.00 02-18-1993 07-001914 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 2200 $11.00 $65.52 $24200.00 02-25-1993 11-046164 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 550 $15.00 $89.35 $8250.00 03-09-1993 04-437654 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 9170 $20.00 $119.13 $183400.00 03-18-1993 07-384114 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 400 $150.00 $893.48 $60000.00 03-23-1993 04-126004 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 76000 $29.00 $172.74 $2204000.00 04-22-1993 07-110324 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 490 $35.00 $208.48 $17150.00 04-22-1993 08-293234 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 2540 $40.00 $238.26 $101600.00 04-22-1993 12-027314 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 1850 $40.00 $238.26 $74000.00 05-12-1993 04-115984 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 4350 $42.00 $250.17 $182700.00 05-20-1993 08-461504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 02 392 $50.00 $297.83 $19600.00 06-02-1993 02-134954 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 02 500 $10.00 $59.57 $5000.00 06-09-1993 02-259904 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 210 $37.00 $220.39 $7770.00 06-23-1993 04-132974 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 06 330 $40.00 $238.26 $13200.00 06-23-1993 06-281104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 21012 $18.00 $107.22 $378216.00 06-29-1993 04-135904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 600 $20.00 $119.13 $12000.00 06-29-1993 04-180644 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 3770 $22.00 $131.04 $82940.00 06-30-1993 04-180444 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 1240 $10.00 $59.57 $12400.00 07-01-1993 07-018744 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 670 $3.00 $17.87 $2010.00 07-01-1993 11-085974 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 12899 $10.00 $59.57 $128990.00 08-04-1993 04-228014 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 6324 $7.00 $41.70 $44268.00 08-05-1993 08-348304 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 11800 $5.00 $29.78 $59000.00 08-10-1993 04-233374 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 60 $50.00 $297.83 $3000.00 08-26-1993 07-118964 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 187 $10.00 $59.57 $1870.00 08-26-1993 11-049314 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 2163 $11.00 $65.52 $23793.00 09-02-1993 11-049844 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 30 $65.00 $387.17 $1950.00 09-21-1993 04-135374 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 177 $20.00 $119.13 $3540.00 09-28-1993 04-116244 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 19900 $10.00 $59.57 $199000.00 09-28-1993 04-233714 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 130 $25.00 $148.91 $3250.00 10-13-1993 04-192004 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 465 $10.00 $59.57 $4650.00 10-14-1993 08-202804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 32975 $31.00 $184.65 $1022225.00 10-14-1993 12-107184 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 4200 $18.00 $107.22 $75600.00 10-26-1993 04-131124 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 32824 $35.00 $208.48 $1148840.00 11-18-1993 07-110334 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 156 $35.00 $208.48 $5460.00 11-18-1993 08-322704 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 6394 $14.00 $75.98 $89516.00 01-11-1994 04-233114 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 350 $6.00 $32.56 $2100.00 01-27-1994 08-280604 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 280 $40.00 $217.08 $11200.00 02-01-1994 04-115404 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 500 $20.00 $108.54 $10000.00 02-03-1994 08-329404 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 936 $15.00 $81.41 $14040.00 02-23-1994 04-131374 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 437 $25.00 $135.68 $10925.00 03-04-1994 07-0Q1104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 640 $5.00 $27.14 $3200.00 03-10-1994 08-316104 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 195 $20.00 $108.54 $3900.00 03-16-1994 04-130864 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 920 $11.00 $59.70 $10120.00 03-18-1994 07-0Q0504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 156 $35.00 $189.95 $5460.00 03-31-1994 08-322704 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 10600 $24.20 $131.33 $256520.00 04-20-1994 04-180244 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 6866 $9.00 $48.84 $61794.00 04-28-1994 11-010304 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 43400 $1.00 $5.43 $43400.00 05-12-1994 12-107234 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 830 $30.00 $162.81 $24900.00 05-17-1994 05-343814 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 01 7800 $25.00 $135.68 $195000.00 05-18-1994 01-318904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 190 $25.00 $135.68 $4750.00 05-19-1994 07-103264 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 560 $10.00 $54.27 $5600.00 05-24-1994 04-138504 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 09 2060 $10.00 $54.27 $20600.00 05-25-1994 09-218204 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 20 $125.00 $678.38 $2500.00 06-01-1994 04-170204 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 21907 $8.00 $43.42 $175256.00 06-16-1994 07-115054 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 9710 $11.00 $59.70 $106810.00 06-23-1994 07-019594 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 43991 $35.00 $189.95 $1539685.00 06-29-1994 04-121774 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 1505 $20.00 $108.54 $30100.00 07-08-1994 07-0Q0704 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 1010 $18.00 $97.69 $18180.00 08-04-1994 11-167844 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 375 $7.30 $39.62 $2737.50 08-25-1994 11-135464 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 5733 $25.00 $135.68 $143325.00 09-21-1994 04-180634 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 14433 $15.00 $81.41 $216495.00 09-22-1994 07-118504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 82 $25.00 $135.68 $2050.00 10-06-1994 07-129004 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 2265 $16.00 $86.83 $36240.00 10-20-1994 07-119684 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 2425 $7.00 $37.99 $16975.00 10-20-1994 12-016204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 8253 $10.00 $54.27 $82530.00 11-18-1994 04-180254 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 10600 $25.00 $135.68 $265000.00 11-22-1994 04-180244 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 03 3735 $45.00 $244.22 $168075.00 11-30-1994 03-348804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 49138 $5.00 $27.14 $245690.00 12-01-1994 11-030114 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 27062 $45.00 $244.22 $1217790.00 12-06-1994 04-233014 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 1500 $25.00 $135.68 $37500.00 12-08-1994 08-268914 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 150 $20.00 $108.54 $3000.00 12-13-1994 04-192204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 10145 $16.00 $86.83 $162320.00 12-14-1994 04-1019U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 6530 $20.00 $108.54 $130600.00 12-16-1994 08-446004 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 1490 $15.00 $86.19 $22350.00 01-10-1995 05-341304 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 650 $8.00 $45.97 $5200.00 01-19-1995 08-347214 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 460 $20.00 $114.93 $9200.00 01-31-1995 04-1271U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 2220 $15.00 $86.19 $33300.00 02-02-1995 08-043504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 190 $10.00 $57.46 $1900.00 02-15-1995 07-1032C4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 1697 $28.00 $160.90 $47516.00 02-16-1995 11-125154 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 20100 $25.00 $143.66 $502500.00 02-22-1995 04-233144 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 1511 $12.00 $68.96 $18132.00 02-23-1995 07-110294 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 7548 $24.00 $137.91 $181152.00 03-02-1995 11-010664 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 02 28 $50.00 $287.31 $1400.00 03-14-1995 02-256814 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 485 $38.00 $218.36 $18430.00 03-14-1995 04-112234 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 130 $10.00 $57.46 $1300.00 03-14-1995 04-130604 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 503 $42.00 $241.34 $21126.00 03-21-1995 04-121584 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 1500 $1.90 $10.92 $2850.00 04-05-1995 04-192214 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 3840 $12.00 $68.96 $46080.00 04-11-1995 04-119654 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 10 140 $35.00 $201.12 $4900.00 04-18-1995 10-351204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 2280 $35.00 $201.12 $79800.00 05-02-1995 04-180754 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 18525 $14.00 $80.45 $259350.00 05-09-1995 04-180264 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 2281 $30.00 $172.39 $68430.00 05-10-1995 04-235774 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 5519 $10.00 $57.46 $55190.00 05-16-1995 05-315414 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 792 $20.00 $114.93 $15840.00 05-18-1995 07-1186C4 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 370 $13.00 $74.70 $4810.00 05-18-1995 11-156564 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 11300 $15.00 $86.19 $169500.00 05-18-1995 12-013404 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 01 418 $50.00 $287.31 $20900.00 06-21-1995 01-338714 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 2327 $20.00 $114.93 $46540.00 06-22-1995 07-116874 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 1420 $51.00 $293.06 $72420.00 07-11-1995 04-129804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 915 $15.00 $86.19 $13725.00 07-12-1995 04-192244 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 915 $15.00 $86.19 $13725.00 07-12-1995 04-192244 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 06 180 $50.00 $287.31 $9000.00 08-08-1995 06-371804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 22852 $15.00 $86.19 $342780.00 08-22-1995 04-377214 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 10 $20.00 $114.93 $200.00 08-22-1995 05-363104 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 5210 $25.00 $143.66 $130250.00 08-31-1995 07-115174 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 2757 $10.00 $57.46 $27570.00 09-14-1995 07-066154 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 01 710 $50.00 $287.31 $35500.00 10-31-1995 01-195624 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 630 $18.00 $103.43 $11340.00 11-02-1995 07-116204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 1880 $15.00 $86.19 $28200.00 11-30-1995 07-112584 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 570 $16.00 $91.94 $9120.00 12-07-1995 07-1209A4 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 1291 $20.00 $114.93 $25820.00 12-14-1995 11-206604 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 2150 $20.00 $114.48 $43000.00 01-04-1996 07-115034 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 10 $46.00 $263.30 $460.00 01-09-1996 05-363104 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 06 2100 $50.00 $286.19 $105000.00 01-10-1996 06-355004 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 800 $125.00 $715.48 $100000.00 01-11-1996 07-119234 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 2075 $10.00 $57.24 $20750.00 01-17-1996 04-233154 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 1530 $15.20 $87.00 $23256.00 01-17-1996 05-366904 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 01 224 $70.00 $400.67 $15680.00 01-30-1996 01-200474 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 2910 $55.00 $314.81 $160050.00 02-08-1996 11-010724 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 41 $30.00 $171.71 $1230.00 02-14-1996 04-192254 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 95 $25.00 $143.10 $2375.00 02-15-1996 07-119944 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 67 $34.00 $194.61 $2278.00 02-27-1996 10-383704 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 2008 $68.45 $391.80 $137447.60 02-29-1996 11-010414 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 67512 $8.00 $45.79 $540096.00 03-14-1996 11-048664 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 7960 $10.00 $57.24 $79600.00 03-21-1996 12-002524 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 580 $11.60 $66.40 $6728.00 04-04-1996 08-322104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 4 $25.00 $143.10 $100.00 04-04-1996 12-054904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 2868 $3.50 $20.03 $10038.00 04-11-1996 11-010014 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 9449 $7.00 $40.07 $66143.00 04-16-1996 04-180054 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 160 $10.00 $57.24 $1600.00 04-17-1996 04-150104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 10795 $7.50 $42.93 $80962.50 04-18-1996 11-184974 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 580 $50.00 $286.19 $29000.00 04-30-1996 04-289714 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 10670 $13.00 $74.41 $138710.00 05-02-1996 07-115044 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 3415 $4.30 $24.61 $14684.50 05-02-1996 11-010034 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 11415 $50.00 $286.19 $570750.00 05-08-1996 04-228294 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 3790 $4.50 $25.76 $17055.00 05-09-1996 11-010384 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 6300 $71.00 $406.39 $447300.00 05-15-1996 05-376504 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 50293 $4.00 $22.90 $201172.00 05-16-1996 11-001914 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 650 $17.00 $97.31 $11050.00 05-21-1996 04-235664 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 340 $30.00 $171.71 $10200.00 05-23-1996 07-125604 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 630 $50.00 $286.19 $31500.00 05-29-1996 04-124484 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 488 $16.00 $91.58 $7808.00 07-02-1996 04-125724 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 05 385 $90.00 $515.14 $34650.00 07-02-1996 05-406804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 01 710 $14.00 $80.13 $9940.00 07-09-1996 01-195624 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 3925 $25.00 $143.10 $98125.00 07-16-1996 04-233104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 06 150 $10.00 $57.24 $1500.00 07-23-1996 06-0257U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 830 $87.00 $497.97 $72210.00 07-24-1996 04-197704 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 3874 $11.00 $62.96 $42614.00 09-05-1996 07-119984 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 860 $33.00 $188.89 $28380.00 09-10-1996 04-135034 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 3992 $29.00 $165.99 $115768.00 09-24-1996 04-196454 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 51 $42.00 $240.40 $2142.00 09-26-1996 08-200104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 1240 $8.70 $49.80 $10788.00 09-26-1996 11-184954 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 7861 $10.00 $57.24 $78610.00 10-01-1996 04-233334 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 1925 $20.00 $114.48 $38500.00 10-03-1996 12-059214 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 20480 $20.00 $114.48 $409600.00 10-17-1996 12-035714 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 604 $30.00 $171.71 $18120.00 10-24-1996 07-169204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 60 $48.00 $274.74 $2880.00 11-14-1996 11-2051U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 27082 $6.00 $34.34 $162492.00 11-14-1996 12-0125U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 771 $20.00 $114.48 $15420.00 11-21-1996 07-1050E4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 888 $27.00 $154.54 $23976.00 11-21-1996 12-0124U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 1900 $12.00 $68.69 $22800.00 12-05-1996 08-281804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 410 $35.00 $200.33 $14350.00 12-10-1996 04-103584 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 8620 $25.00 $137.20 $215500.00 02-06-1997 12-0155U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 310 $8.00 $43.90 $2480.00 02-20-1997 07-105204 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 380 $23.00 $126.22 $8740.00 02-25-1997 10-402504 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 130 $33.32 $182.86 $4331.60 02-27-1997 07-120824 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 760 $11.00 $60.37 $8360.00 03-06-1997 07-1028C4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 500 $41.00 $225.01 $20500.00 03-13-1997 07-120734 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 25310 $15.00 $82.32 $379650.00 04-02-1997 12-012614 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 16639 $11.00 $60.37 $183029.00 04-03-1997 07-002634 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 1880 $25.00 $137.20 $47000.00 04-08-1997 02-260964 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 31687 $9.00 $49.39 $285183.00 04-17-1997 12-0124V4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 465 $15.00 $82.32 $6975.00 04-24-1997 07-402274 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 566 $40.00 $219.52 $22640.00 04-24-1997 11-051504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 720 $100.00 $548.80 $72000.00 04-30-1997 06-343544 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 1015 $28.38 $155.75 $28805.70 05-15-1997 07-129914 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 27393 $16.00 $87.81 $438288.00 05-15-1997 08-367614 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 390 $10.00 $54.88 $3900.00 05-28-1997 10-414904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 7470 $40.00 $219.52 $298800.00 06-05-1997 08-350704 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 2110 $19.00 $104.27 $40090.00 06-12-1997 07-147534 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 13353 $10.00 $54.88 $133530.00 06-12-1997 12-012624 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 490 $75.00 $411.60 $36750.00 06-17-1997 03-432904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 430 $24.00 $131.71 $10320.00 06-17-1997 04-135164 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 1470 $38.50 $211.29 $56595.00 06-24-1997 04-496914 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 05 2480 $17.00 $93.30 $42160.00 06-25-1997 05-424004 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2410 $27.00 $148.18 $65070.00 07-10-1997 07-129924 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 160 $50.00 $274.40 $8000.00 07-17-1997 07-168404 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 16174 $25.00 $137.20 $404350.00 07-17-1997 08-367624 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 1020 $46.00 $252.45 $46920.00 08-07-1997 07-120794 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 2637 $42.00 $230.50 $110754.00 08-12-1997 04-497304 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 15 $25.00 $137.20 $375.00 08-19-1997 10-279434 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 297 $130.00 $713.44 $38610.00 08-21-1997 07-028014 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 1350 $172.00 $943.94 $232200.00 08-27-1997 03-0A0504 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 20 $30.00 $164.64 $600.00 09-03-1997 10-328504 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 4865 $25.00 $137.20 $121625.00 09-18-1997 12-059224 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 2519 $70.00 $384.16 $176330.00 09-23-1997 04-377194 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 630 $100.00 $548.80 $63000.00 10-01-1997 03-0A4904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 725 $40.00 $219.52 $29000.00 10-15-1997 04-180154 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 01 5 $150.00 $823.20 $750.00 10-16-1997 01-370704 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 14500 $10.00 $54.88 $145000.00 10-23-1997 12-012634 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 113 $30.00 $164.64 $3390.00 10-28-1997 03-362104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 9700 $12.00 $65.86 $116400.00 11-13-1997 08-4632V4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 430 $24.00 $131.71 $10320.00 11-18-1997 04-135164 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 334 $15.00 $82.32 $5010.00 12-17-1997 04-133164 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 05 38 $1000.00 $5233.21 $38000.00 01-07-1998 05-453604 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 9988 $10.00 $52.33 $99880.00 01-08-1998 12-059234 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 2260 $10.00 $52.33 $22600.00 02-05-1998 08-204304 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 1633 $12.84 $67.19 $20967.72 02-05-1998 11-022144 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 600 $25.00 $130.83 $15000.00 02-05-1998 11-059104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 195 $30.00 $157.00 $5850.00 03-19-1998 07-126234 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 355 $30.00 $157.00 $10650.00 03-19-1998 07-187104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 280 $50.00 $261.66 $14000.00 03-25-1998 04-174914 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 80 $100.00 $523.32 $8000.00 03-26-1998 07-174504 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 14397 $30.00 $157.00 $431910.00 03-26-1998 12-035724 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 1220 $20.00 $104.66 $24400.00 04-07-1998 10-426014 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 1440 $18.00 $94.20 $25920.00 04-09-1998 12-059244 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 780 $60.00 $313.99 $46800.00 04-15-1998 06-371004 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 348 $12.50 $65.42 $4350.00 04-23-1998 07-4A8604 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 2120 $18.00 $94.20 $38160.00 04-30-1998 08-368204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 2290 $13.00 $68.03 $29770.00 05-07-1998 11-183964 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 1754 $35.00 $183.16 $61390.00 05-14-1998 11-125144 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 3100 $35.00 $183.16 $108500.00 05-20-1998 04-228354 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 255 $85.00 $444.82 $21675.00 05-20-1998 05-455104 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 270 $50.00 $261.66 $13500.00 05-21-1998 04-254504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 22 $69.00 $361.09 $1518.00 05-21-1998 11-0301J4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 200 $40.00 $209.33 $8000.00 05-21-1998 12-081604 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 04 16200 $5.00 $26.17 $81000.00 05-27-1998 04-233924 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 3890 $15.00 $78.50 $58350.00 06-04-1998 12-042524 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 190 $90.00 $470.99 $17100.00 06-09-1998 10-491304 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 20 $115.00 $601.82 $2300.00 06-16-1998 02-299404 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 210 $62.00 $324.46 $13020.00 06-16-1998 06-3491U4 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 1248 $36.00 $188.40 $44928.00 07-02-1998 07-4F4904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 17770 $7.00 $36.63 $124390.00 07-09-1998 11-001924 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 301 $6.00 $31.40 $1806.00 07-09-1998 11-062104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 2680 $21.02 $110.00 $56333.60 07-30-1998 07-1209C4 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 1120 $40.00 $209.33 $44800.00 08-06-1998 07-120964 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 670 $31.00 $162.23 $20770.00 08-13-1998 07-120994 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 1386 $15.00 $78.50 $20790.00 08-13-1998 12-059254 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 1730 $13.00 $68.03 $22490.00 08-25-1998 06-359534 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 680 $54.00 $282.59 $36720.00 08-27-1998 07-120984 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 1600 $10.00 $52.33 $16000.00 09-02-1998 04-438614 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 61 $23.00 $120.36 $1403.00 09-03-1998 08-259404 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 45 $70.00 $366.32 $3150.00 09-10-1998 12-0294U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 05 1710 $87.70 $458.95 $149967.00 09-16-1998 05-430004 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 880 $50.00 $261.66 $44000.00 09-30-1998 02-277504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 910 $25.00 $130.83 $22750.00 09-30-1998 04-181784 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 167 $60.00 $313.99 $10020.00 10-08-1998 04-258604 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 5390 $110.00 $575.65 $592900.00 10-15-1998 07-118084 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 595 $21.00 $109.90 $12495.00 10-15-1998 08-007114 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 12 2811 $9.00 $47.10 $25299.00 10-22-1998 12-0357A4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 465 $15.00 $78.50 $6975.00 10-27-1998 04-235104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 6670 $45.00 $235.49 $300150.00 10-29-1998 11-010744 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 06 314 $50.00 $261.66 $15700.00 11-03-1998 06-278614 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 8599 $14.00 $73.27 $120386.00 11-19-1998 12-013324 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 05 1060 $20.00 $104.66 $21200.00 12-01-1998 05-3090U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 1105 $11.00 $57.57 $12155.00 12-17-1998 11-048074 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 16296 $18.00 $87.92 $293328.00 01-07-1999 12-013314 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 3950 $25.00 $122.11 $98750.00 03-11-1999 07-119464 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 21700 $12.00 $58.61 $260400.00 03-18-1999 12-013344 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 14400 $17.00 $83.03 $244800.00 03-25-1999 12-013334 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 120 $20.00 $97.69 $2400.00 04-08-1999 07-172124 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 600 $40.00 $195.37 $24000.00 04-08-1999 07-4F8804 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 445 $60.00 $293.06 $26700.00 04-13-1999 10-4483U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 120 $50.00 $244.22 $6000.00 04-20-1999 02-346604 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 940 $40.00 $195.37 $37600.00 04-29-1999 07-102914 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 100 $32.00 $156.30 $3200.00 05-06-1999 08-445204 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 01 185 $15.00 $73.27 $2775.00 05-12-1999 01-358004 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 43 $65.00 $317.48 $2795.00 05-12-1999 04-135384 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 2200 $8.00 $39.07 $17600.00 05-13-1999 12-046124 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 2160 $15.00 $73.27 $32400.00 05-21-1999 12-069514 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 9082 $25.00 $122.11 $227050.00 05-27-1999 11-0019U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 1100 $23.50 $114.78 $25850.00 05-27-1999 11-147024 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 468 $50.00 $244.22 $23400.00 06-02-1999 04-006094 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 01 560 $15.00 $73.27 $8400.00 06-08-1999 01-386604 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 7050 $59.00 $288.18 $415950.00 06-10-1999 07-1667U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 05 4361 $20.00 $97.69 $87220.00 06-16-1999 05-345414 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 5092 $25.00 $122.11 $127300.00 06-24-1999 12-0678U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 2174 $20.00 $97.69 $43480.00 06-30-1999 04-228914 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 7960 $7.00 $34.19 $55720.00 07-01-1999 07-003104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 120 $50.00 $244.22 $6000.00 07-07-1999 03-3696U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 34 $155.00 $757.07 $5270.00 07-21-1999 04-242104 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 06 470 $22.00 $107.46 $10340.00 08-04-1999 06-305514 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 28 $350.00 $1709.52 $9800.00 08-05-1999 11-064624 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 380 $53.55 $261.56 $20349.00 08-26-1999 12-0827U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 533 $7.00 $34.19 $3731.00 10-07-1999 11-001934 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 920 $110.00 $537.28 $101200.00 10-21-1999 08-315004 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 180 $200.00 $976.87 $36000.00 12-21-1999 04-438634 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 675 $50.00 $237.10 $33750.00 01-11-2000 04-013014 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 88 $35.00 $165.97 $3080.00 01-12-2000 02-340004 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 3300 $15.00 $71.13 $49500.00 01-12-2000 04-4874Q4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 226 $17.50 $82.99 $3955.00 01-13-2000 11-0722U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 404 $60.00 $284.52 $24240.00 02-02-2000 04-228924 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 5410 $10.00 $47.42 $54100.00 02-10-2000 07-1957U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 76 $38.00 $180.20 $2888.00 03-23-2000 12-060904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 51 $29.50 $139.89 $1504.50 03-23-2000 12-074824 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 382 $24.00 $113.81 $9168.00 04-06-2000 07-178304 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 900 $24.50 $116.18 $22050.00 04-18-2000 04-045034 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 1120 $20.00 $94.84 $22400.00 04-18-2000 04-151254 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 840 $19.20 $91.05 $16128.00 04-20-2000 07-103354 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 404 $53.00 $251.33 $21412.00 05-04-2000 12-0827U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 110 $100.00 $474.21 $11000.00 05-18-2000 07-2M8304 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 55 $114.00 $540.60 $6270.00 05-25-2000 08-453504 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 318 $22.00 $104.33 $6996.00 06-01-2000 08-377504 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 220 $57.00 $270.30 $12540.00 06-07-2000 04-201904 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 210 $65.00 $308.23 $13650.00 06-08-2000 08-3564U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 137 $20.00 $94.84 $2740.00 06-22-2000 07-172164 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 01 730 $9.00 $42.68 $6570.00 07-26-2000 01-365604 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2100 $20.00 $94.84 $42000.00 08-10-2000 07-1264A4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 170 $45.00 $213.39 $7650.00 08-30-2000 04-244804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 01 2000 $20.00 $94.84 $40000.00 09-12-2000 01-376204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 48935 $45.00 $213.39 $2202075.00 09-21-2000 07-126494 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 120 $45.00 $213.39 $5400.00 09-28-2000 11-064614 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 681 $46.00 $218.14 $31326.00 10-12-2000 07-191004 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 11 7652 $27.00 $128.04 $206604.00 10-12-2000 11-010734 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 880 $110.00 $521.63 $96800.00 10-17-2000 03-0A7814 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 21904 $15.00 $71.13 $328560.00 10-20-2000 12-0695U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 3037 $50.00 $237.10 $151850.00 10-20-2000 12-087704 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 08 4810 $20.00 $94.84 $96200.00 10-26-2000 08-340804 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 1280 $40.00 $189.68 $51200.00 11-02-2000 07-172204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 3934 $60.00 $284.52 $236040.00 11-14-2000 03-3A21U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 677 $10.00 $47.42 $6770.00 11-28-2000 03-382904 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 1480 $100.00 $474.21 $148000.00 12-06-2000 04-0T0504 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 367 $8.75 $41.49 $3211.25 12-06-2000 07-117044 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 12276 $10.00 $47.42 $122760.00 12-07-2000 12-083804 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 470 $32.00 $151.75 $15040.00 12-12-2000 04-253504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 141994 $30.00 $142.26 $4259820.00 12-14-2000 07-1224U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 170 $25.00 $109.35 $4250.00 01-03-2001 03-0A9904 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 09 230 $350.00 $1530.91 $80500.00 01-09-2001 09-214114 1   TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 9825 $25.00 $109.35 $245625.00 01-11-2001 07-172154 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 550 $20.00 $87.48 $11000.00 01-30-2001 03-4416U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 3840 $25.00 $109.35 $96000.00 02-01-2001 08-406804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 248.3 $90.00 $393.66 $22347.00 03-22-2001 07-195104 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 110 $55.00 $240.57 $6050.00 04-19-2001 11-172864 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 450 $15.00 $65.61 $6750.00 05-02-2001 10-3404U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 33800 $8.50 $37.18 $287300.00 05-10-2001 08-4353U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 170 $20.00 $87.48 $3400.00 05-10-2001 12-062004 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 2515 $35.00 $153.09 $88025.00 05-15-2001 03-366404 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 1490 $225.00 $984.16 $335250.00 05-15-2001 04-0S9404 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 4199 $21.00 $91.85 $88179.00 05-31-2001 12-0408F4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 975 $16.14 $70.60 $15736.50 06-13-2001 04-285524 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 1480 $25.00 $109.35 $37000.00 06-20-2001 04-0T0504 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 650 $10.00 $43.74 $6500.00 06-21-2001 12-0408E4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 73 $50.00 $218.70 $3650.00 06-28-2001 07-195324 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 155 $20.00 $87.48 $3100.00 08-07-2001 03-2A8604 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 05 1370 $50.00 $218.70 $68500.00 08-07-2001 05-0161U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 180 $40.00 $174.96 $7200.00 08-22-2001 04-0S8704 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 3068 $80.00 $349.92 $245440.00 08-23-2001 11-0479K4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 323 $30.00 $131.22 $9690.00 08-23-2001 11-185944 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 50 $100.00 $437.40 $5000.00 08-30-2001 07-111574 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 40 $30.00 $131.22 $1200.00 08-30-2001 11-234714 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 358 $12.00 $52.49 $4296.00 09-06-2001 07-1264G4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 3478 $8.00 $34.99 $27824.00 09-18-2001 06-342324 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 1455 $14.00 $61.24 $20370.00 09-20-2001 11-073404 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 2520 $104.00 $454.90 $262080.00 10-04-2001 08-4221U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 480 $25.00 $109.35 $12000.00 10-16-2001 04-4C0204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 180 $27.00 $118.10 $4860.00 10-31-2001 04-045044 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) CY 07 59837 $11.00 $48.11 $658207.00 11-01-2001 07-1069U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 1845 $24.00 $104.98 $44280.00 11-01-2001 07-201304 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 7165 $40.00 $174.96 $286600.00 11-14-2001 04-006064 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 780 $18.00 $78.73 $14040.00 11-14-2001 04-0T1414 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 180 $30.00 $131.22 $5400.00 11-15-2001 07-1760U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 05 4240 $17.58 $76.90 $74539.20 11-28-2001 05-0161A4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 620 $30.00 $131.22 $18600.00 12-12-2001 04-226124 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 160 $25.00 $109.35 $4000.00 12-13-2001 12-053284 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $20.00 $94.54 $10000.00 01-10-2002 12-040894 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $25.00 $118.17 $12500.00 01-10-2002 12-040894 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $30.00 $141.80 $15000.00 01-10-2002 12-040894 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $13.00 $61.45 $6500.00 01-10-2002 12-040894 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $10.00 $47.27 $5000.00 01-10-2002 12-040894 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $12.00 $56.72 $6000.00 01-10-2002 12-040894 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $48.88 $231.04 $24440.00 01-10-2002 12-040894 7 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $25.00 $118.17 $12500.00 01-10-2002 12-040894 8 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 500 $22.00 $103.99 $11000.00 01-10-2002 12-040894 9 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 3152 $45.00 $212.70 $141840.00 01-23-2002 10-1A5404 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 3152 $25.00 $118.17 $78800.00 01-23-2002 10-1A5404 2    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 3152 $21.00 $99.26 $66192.00 01-23-2002 10-1A5404 3    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 3152 $63.00 $297.79 $198576.00 01-23-2002 10-1A5404 4    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 3152 $40.02 $189.17 $126143.04 01-23-2002 10-1A5404 5    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 64887 $20.00 $94.54 $1297740.00 01-24-2002 11-0301U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 64887 $15.00 $70.90 $973305.00 01-24-2002 11-0301U4 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 64887 $10.00 $47.27 $648870.00 01-24-2002 11-0301U4 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 64887 $24.00 $113.44 $1557288.00 01-24-2002 11-0301U4 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 64887 $30.00 $141.80 $1946610.00 01-24-2002 11-0301U4 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 64887 $27.00 $127.62 $1751949.00 01-24-2002 11-0301U4 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 82 $50.00 $236.34 $4100.00 02-13-2002 04-006044 1   TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 82 $52.50 $248.16 $4305.00 02-13-2002 04-006044 2   TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 82 $60.00 $283.61 $4920.00 02-13-2002 04-006044 3   TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 82 $26.00 $122.90 $2132.00 02-13-2002 04-006044 4   TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 82 $53.00 $250.52 $4346.00 02-13-2002 04-006044 5   TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 82 $40.00 $189.07 $3280.00 02-13-2002 04-006044 6   TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $80.00 $378.14 $174400.00 02-21-2002 07-191304 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $99.00 $467.95 $215820.00 02-21-2002 07-191304 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $30.00 $141.80 $65400.00 02-21-2002 07-191304 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $15.00 $70.90 $32700.00 02-21-2002 07-191304 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $30.00 $141.80 $65400.00 02-21-2002 07-191304 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $15.00 $70.90 $32700.00 02-21-2002 07-191304 7 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 14400 $8.00 $37.81 $115200.00 02-28-2002 08-3555U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 14400 $12.00 $56.72 $172800.00 02-28-2002 08-3555U4 2 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 14400 $16.00 $75.63 $230400.00 02-28-2002 08-3555U4 3 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 14400 $24.00 $113.44 $345600.00 02-28-2002 08-3555U4 4 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 14400 $24.00 $113.44 $345600.00 02-28-2002 08-3555U4 5 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 14400 $38.00 $179.62 $547200.00 02-28-2002 08-3555U4 6 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 710 $15.00 $70.90 $10650.00 03-07-2002 12-0008E4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 710 $20.00 $94.54 $14200.00 03-07-2002 12-0008E4 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 710 $38.00 $179.62 $26980.00 03-07-2002 12-0008E4 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 710 $22.00 $103.99 $15620.00 03-07-2002 12-0008E4 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 710 $20.00 $94.54 $14200.00 03-07-2002 12-0008E4 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 710 $300.00 $1418.03 $213000.00 03-07-2002 12-0008E4 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 710 $45.00 $212.70 $31950.00 03-07-2002 12-0008E4 7 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 710 $35.00 $165.44 $24850.00 03-07-2002 12-0008E4 8 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 850 $95.25 $450.23 $80962.50 03-26-2002 10-2A50U4 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 850 $75.00 $354.51 $63750.00 03-26-2002 10-2A50U4 2 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 850 $57.00 $269.43 $48450.00 03-26-2002 10-2A50U4 3 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 850 $75.00 $354.51 $63750.00 03-26-2002 10-2A50U4 4 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 2380 $20.00 $94.54 $47600.00 03-27-2002 10-1A7004 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 2380 $20.00 $94.54 $47600.00 03-27-2002 10-1A7004 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 2380 $7.00 $33.09 $16660.00 03-27-2002 10-1A7004 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 2380 $10.00 $47.27 $23800.00 03-27-2002 10-1A7004 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 10 2380 $50.00 $236.34 $119000.00 03-27-2002 10-1A7004 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 850 $16.85 $79.65 $14322.50 03-28-2002 07-0607U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 850 $25.00 $118.17 $21250.00 03-28-2002 07-0607U4 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 850 $21.00 $99.26 $17850.00 03-28-2002 07-0607U4 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 850 $20.00 $94.54 $17000.00 03-28-2002 07-0607U4 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 850 $35.00 $165.44 $29750.00 03-28-2002 07-0607U4 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 850 $21.00 $99.26 $17850.00 03-28-2002 07-0607U4 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 850 $40.00 $189.07 $34000.00 03-28-2002 07-0607U4 7 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 850 $30.00 $141.80 $25500.00 03-28-2002 07-0607U4 8 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 1116 $100.00 $472.68 $111600.00 04-09-2002 03-3546U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 1116 $100.00 $472.68 $111600.00 04-09-2002 03-3546U4 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $35.00 $165.44 $76300.00 04-25-2002 07-191304 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $49.00 $231.61 $106820.00 04-25-2002 07-191304 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $40.00 $189.07 $87200.00 04-25-2002 07-191304 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $15.00 $70.90 $32700.00 04-25-2002 07-191304 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $57.00 $269.43 $124260.00 04-25-2002 07-191304 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2180 $25.00 $118.17 $54500.00 04-25-2002 07-191304 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 77 $94.00 $444.32 $7238.00 05-08-2002 03-0C2704 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 03 77 $132.00 $623.93 $10164.00 05-08-2002 03-0C2704 2    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $43.50 $205.61 $10570.50 05-09-2002 12-073704 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $50.00 $236.34 $12150.00 05-09-2002 12-073704 2    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $60.00 $283.61 $14580.00 05-09-2002 12-073704 3    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $40.00 $189.07 $9720.00 05-09-2002 12-073704 4    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $34.40 $162.60 $8359.20 05-09-2002 12-073704 5    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $41.00 $193.80 $9963.00 05-09-2002 12-073704 6    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $30.00 $141.80 $7290.00 05-09-2002 12-073704 7    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $75.00 $354.51 $18225.00 05-09-2002 12-073704 8    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $50.00 $236.34 $12150.00 05-09-2002 12-073704 9    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $59.42 $280.88 $14440.01 05-09-2002 12-073704 10    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $75.00 $354.51 $18225.00 05-09-2002 12-073704 11    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 243 $28.80 $136.13 $6998.40 05-09-2002 12-073704 12    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 100 $27.00 $127.62 $2700.00 05-23-2002 08-4047U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 100 $22.00 $103.99 $2200.00 05-23-2002 08-4047U4 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 100 $15.00 $70.90 $1500.00 05-23-2002 08-4047U4 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 100 $35.60 $168.27 $3560.00 05-23-2002 08-4047U4 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 100 $30.00 $141.80 $3000.00 05-23-2002 08-4047U4 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 08 100 $45.00 $212.70 $4500.00 05-23-2002 08-4047U4 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 7270 $15.00 $70.90 $109050.00 06-06-2002 07-104954 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 7270 $74.00 $349.78 $537980.00 06-06-2002 07-104954 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 7270 $60.00 $283.61 $436200.00 06-06-2002 07-104954 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 7270 $28.00 $132.35 $203560.00 06-06-2002 07-104954 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 7270 $65.00 $307.24 $472550.00 06-06-2002 07-104954 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 7270 $30.00 $141.80 $218100.00 06-06-2002 07-104954 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 12840 $8.00 $37.81 $102720.00 06-18-2002 06-342424 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 12840 $14.00 $66.17 $179760.00 06-18-2002 06-342424 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 12840 $42.00 $198.52 $539280.00 06-18-2002 06-342424 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 12840 $6.00 $28.36 $77040.00 06-18-2002 06-342424 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 12840 $70.00 $330.87 $898800.00 06-18-2002 06-342424 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 425 $27.00 $127.62 $11475.00 06-20-2002 11-172824 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 425 $14.00 $66.17 $5950.00 06-20-2002 11-172824 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 425 $50.00 $236.34 $21250.00 06-20-2002 11-172824 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 425 $30.00 $141.80 $12750.00 06-20-2002 11-172824 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 425 $25.00 $118.17 $10625.00 06-20-2002 11-172824 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 425 $25.00 $118.17 $10625.00 06-20-2002 11-172824 6 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 11 425 $8.00 $37.81 $3400.00 06-20-2002 11-172824 7 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2867 $21.00 $99.26 $60207.00 07-11-2002 07-147804 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2867 $47.00 $222.16 $134749.00 07-11-2002 07-147804 2 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2867 $42.00 $198.52 $120414.00 07-11-2002 07-147804 3 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2867 $58.00 $274.15 $166286.00 07-11-2002 07-147804 4 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2867 $200.00 $945.35 $573400.00 07-11-2002 07-147804 5 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 1490 $50.00 $236.34 $74500.00 07-16-2002 04-006054 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 463 $175.00 $827.19 $81025.00 07-18-2002 12-0A2204 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 463 $130.00 $614.48 $60190.00 07-18-2002 12-0A2204 2 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 12 463 $350.00 $1654.37 $162050.00 07-18-2002 12-0A2204 3 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 04 38 $50.00 $236.34 $1900.00 07-24-2002 04-251304 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 06 14 $235.00 $1110.79 $3290.00 07-24-2002 06-456404 1    
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 350 $30.00 $141.80 $10500.00 07-25-2002 07-166504 1 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 350 $40.00 $189.07 $14000.00 07-25-2002 07-166504 2 M  
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 440 $33.00 $155.98 $14520.00 08-20-2002 02-261204 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 440 $45.00 $212.70 $19800.00 08-20-2002 02-261204 2 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 440 $40.00 $189.07 $17600.00 08-20-2002 02-261204 3 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 440 $30.00 $141.80 $13200.00 08-20-2002 02-261204 4 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 02 440 $101.00 $477.40 $44440.00 08-20-2002 02-261204 5 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2833 $67.00 $316.69 $189811.00 09-05-2002 07-0533U4 1 M TRO
192037 - STRUCTURE EXCAVATION (RETAINING WALL) M3 07 2833 $18.00 $85.08 $50994.00 09-05-2002 07-0533U4 2 M TRO
MORE THAN 500 RESULTS RETURNED. ONLY 500 ROWS SHOWN.
SUMMARY Unmodified Adjusted    
Average Price/Unit: $ Avg No. Units
Std Dev. (of Unit Price): ±$ Rows Selected
Weighted Avg.: $ Rows Returned
Minimum Price/Unit: $    
Maximum Price/Unit: $    

| Back | New Search |

PARAMETERS: Item = 192037; District=All; Year=All; Convert=No; Bidders=All Bidders
TIMESTAMP: 09/26/2026 21:44:18
CURRENT 12-MO INDEX (CHCCI (2020 Base)): 146.53