CALIFORNIA DEPARTMENT OF TRANSPORTATION - CONTRACT COST DATA

Select Item No. / Description Unit Dist Qty Unit
Price
Adj
Price
Total Bid Open
Date
Contract
No.
Bid M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 11 1049 $240.00 $1373.72 $251760.00 03-14-1996 11-048664 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1663 $38.00 $217.51 $63194.00 09-10-1996 04-496424 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 930 $20.00 $114.48 $18600.00 10-17-1996 12-035714 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 150 $30.00 $164.64 $4500.00 02-06-1997 12-0155U4 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4943 $40.00 $219.52 $197720.00 05-15-1997 08-367614 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 01 132 $100.00 $523.32 $13200.00 06-09-1998 01-332304 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1400 $60.00 $313.99 $84000.00 08-11-1998 04-0S1314 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 06 9100 $15.00 $78.50 $136500.00 11-03-1998 06-278614 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 390 $100.00 $488.43 $39000.00 09-15-1999 04-268104 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 340 $100.00 $474.21 $34000.00 01-11-2000 04-013014 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 09 540 $30.00 $142.26 $16200.00 03-15-2000 09-213114 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 45 $67.30 $319.14 $3028.50 04-18-2000 04-045034 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 01 1873 $26.00 $123.29 $48698.00 07-12-2000 01-294704 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 07 124 $173.00 $820.38 $21452.00 10-12-2000 07-191004 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2344 $50.00 $218.70 $117200.00 12-12-2001 04-226124 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 160 $27.00 $127.62 $4320.00 07-16-2002 04-006054 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 28 $608.00 $2873.88 $17024.00 07-30-2002 05-0H6304 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 28 $608.00 $2873.88 $17024.00 07-30-2002 05-0H6304 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 28 $550.00 $2599.73 $15400.00 07-30-2002 05-0H6304 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 28 $200.00 $945.35 $5600.00 07-30-2002 05-0H6304 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $63.00 $297.79 $52290.00 09-12-2002 08-334834 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $40.00 $189.07 $33200.00 09-12-2002 08-334834 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $16.00 $75.63 $13280.00 09-12-2002 08-334834 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $10.00 $47.27 $8300.00 09-12-2002 08-334834 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $30.00 $141.80 $24900.00 09-12-2002 08-334834 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $23.00 $108.72 $19090.00 09-12-2002 08-334834 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $80.00 $378.14 $66400.00 09-12-2002 08-334834 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $15.00 $70.90 $12450.00 09-12-2002 08-334834 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $35.00 $165.44 $29050.00 09-12-2002 08-334834 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $60.00 $283.61 $49800.00 09-12-2002 08-334834 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 830 $14.00 $66.17 $11620.00 09-12-2002 08-334834 11 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 07 11279 $11.00 $51.99 $124069.00 09-26-2002 07-1198U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 07 11279 $11.00 $51.99 $124069.00 09-26-2002 07-1198U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 07 11279 $16.00 $75.63 $180464.00 09-26-2002 07-1198U4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 340 $31.00 $138.91 $10540.00 07-24-2003 08-1A76U4 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 340 $130.00 $582.54 $44200.00 07-24-2003 08-1A76U4 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 340 $160.00 $716.97 $54400.00 07-24-2003 08-1A76U4 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 340 $42.39 $189.95 $14412.60 07-24-2003 08-1A76U4 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 780 $36.20 $162.21 $28236.00 09-17-2003 04-228444 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 780 $39.00 $174.76 $30420.00 09-17-2003 04-228444 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 780 $20.00 $89.62 $15600.00 09-17-2003 04-228444 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 780 $50.00 $224.05 $39000.00 09-17-2003 04-228444 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 780 $70.00 $313.67 $54600.00 09-17-2003 04-228444 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 780 $80.00 $358.48 $62400.00 09-17-2003 04-228444 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 773 $71.00 $318.15 $54883.00 11-13-2003 08-446514 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 773 $70.00 $313.67 $54110.00 11-13-2003 08-446514 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 773 $45.00 $201.65 $34785.00 11-13-2003 08-446514 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 773 $125.00 $560.13 $96625.00 11-13-2003 08-446514 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 773 $110.00 $492.91 $85030.00 11-13-2003 08-446514 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 773 $70.00 $313.67 $54110.00 11-13-2003 08-446514 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 3700 $25.00 $74.01 $92500.00 06-10-2004 11-080914 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 3700 $12.00 $35.52 $44400.00 06-10-2004 11-080914 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 3700 $20.00 $59.20 $74000.00 06-10-2004 11-080914 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 3700 $50.00 $148.01 $185000.00 06-10-2004 11-080914 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 3700 $13.00 $38.48 $48100.00 06-10-2004 11-080914 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2880 $24.00 $61.91 $69120.00 01-11-2005 04-1123C4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2880 $24.00 $61.91 $69120.00 01-11-2005 04-1123C4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2880 $8.00 $20.64 $23040.00 01-11-2005 04-1123C4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2880 $40.00 $103.19 $115200.00 01-11-2005 04-1123C4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2880 $12.00 $30.96 $34560.00 01-11-2005 04-1123C4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2880 $20.00 $51.60 $57600.00 01-11-2005 04-1123C4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2880 $35.00 $90.29 $100800.00 01-11-2005 04-1123C4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2880 $400.00 $1031.90 $1152000.00 01-11-2005 04-1123C4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 210 $60.00 $154.79 $12600.00 05-10-2005 04-278204 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 210 $172.73 $445.60 $36273.30 05-10-2005 04-278204 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 210 $125.00 $322.47 $26250.00 05-10-2005 04-278204 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 54 $164.00 $423.08 $8856.00 05-26-2005 12-0A7614 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 54 $450.00 $1160.89 $24300.00 05-26-2005 12-0A7614 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 54 $135.00 $348.27 $7290.00 05-26-2005 12-0A7614 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 54 $200.00 $515.95 $10800.00 05-26-2005 12-0A7614 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 620 $150.00 $386.96 $93000.00 08-16-2005 04-1S3224 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 620 $105.00 $270.87 $65100.00 08-16-2005 04-1S3224 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 620 $115.00 $296.67 $71300.00 08-16-2005 04-1S3224 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 620 $150.00 $386.96 $93000.00 08-16-2005 04-1S3224 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2015 $70.00 $180.58 $141050.00 11-16-2005 04-263704 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2015 $18.00 $46.44 $36270.00 11-16-2005 04-263704 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2015 $40.00 $103.19 $80600.00 11-16-2005 04-263704 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2015 $4.00 $10.32 $8060.00 11-16-2005 04-263704 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2015 $56.00 $144.47 $112840.00 11-16-2005 04-263704 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2015 $26.00 $67.07 $52390.00 11-16-2005 04-263704 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2015 $100.00 $257.98 $201500.00 11-16-2005 04-263704 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 860 $10.00 $24.92 $8600.00 01-24-2006 05-129104 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 860 $50.00 $124.60 $43000.00 01-24-2006 05-129104 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 860 $100.00 $249.20 $86000.00 01-24-2006 05-129104 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 860 $50.00 $124.60 $43000.00 01-24-2006 05-129104 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 860 $30.00 $74.76 $25800.00 01-24-2006 05-129104 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $44.00 $109.65 $11880.00 11-02-2006 12-056214 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $120.00 $299.04 $32400.00 11-02-2006 12-056214 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $80.00 $199.36 $21600.00 11-02-2006 12-056214 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $45.00 $112.14 $12150.00 11-02-2006 12-056214 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $25.00 $62.30 $6750.00 11-02-2006 12-056214 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $45.00 $112.14 $12150.00 11-02-2006 12-056214 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $110.00 $274.12 $29700.00 11-02-2006 12-056214 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $100.00 $249.20 $27000.00 11-02-2006 12-056214 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $190.00 $473.48 $51300.00 11-02-2006 12-056214 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 12 270 $90.00 $224.28 $24300.00 11-02-2006 12-056214 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 820 $50.00 $124.60 $41000.00 11-14-2006 04-1123U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 820 $25.00 $62.30 $20500.00 11-14-2006 04-1123U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 872 $50.00 $125.24 $43600.00 01-25-2007 11-224314 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 872 $82.00 $205.39 $71504.00 01-25-2007 11-224314 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 872 $50.00 $125.24 $43600.00 01-25-2007 11-224314 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 872 $70.00 $175.34 $61040.00 01-25-2007 11-224314 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 872 $110.00 $275.53 $95920.00 01-25-2007 11-224314 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 872 $42.00 $105.20 $36624.00 01-25-2007 11-224314 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 872 $70.00 $175.34 $61040.00 01-25-2007 11-224314 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 872 $19.00 $47.59 $16568.00 01-25-2007 11-224314 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1720 $35.00 $87.67 $60200.00 04-24-2007 04-174934 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1720 $33.00 $82.66 $56760.00 04-24-2007 04-174934 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1720 $90.00 $225.43 $154800.00 04-24-2007 04-174934 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 1750 $50.00 $125.24 $87500.00 06-28-2007 11-2358U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 1750 $95.00 $237.95 $166250.00 06-28-2007 11-2358U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 1750 $160.00 $400.77 $280000.00 06-28-2007 11-2358U4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 1750 $50.00 $125.24 $87500.00 06-28-2007 11-2358U4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 1750 $60.00 $150.29 $105000.00 06-28-2007 11-2358U4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 1750 $70.00 $175.34 $122500.00 06-28-2007 11-2358U4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2860 $50.00 $125.24 $143000.00 08-08-2007 04-2S2204 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2860 $38.00 $95.18 $108680.00 08-08-2007 04-2S2204 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2860 $82.00 $205.39 $234520.00 08-08-2007 04-2S2204 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2860 $90.00 $225.43 $257400.00 08-08-2007 04-2S2204 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2860 $84.00 $210.40 $240240.00 08-08-2007 04-2S2204 5 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 2520 $55.00 $137.76 $138600.00 12-11-2007 05-0K3204 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 2520 $75.00 $187.86 $189000.00 12-11-2007 05-0K3204 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 2520 $80.00 $200.38 $201600.00 12-11-2007 05-0K3204 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 2520 $98.00 $245.47 $246960.00 12-11-2007 05-0K3204 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 2520 $120.00 $300.57 $302400.00 12-11-2007 05-0K3204 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 2520 $160.00 $400.77 $403200.00 12-11-2007 05-0K3204 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 2520 $170.00 $425.81 $428400.00 12-11-2007 05-0K3204 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 2520 $80.00 $200.38 $201600.00 12-11-2007 05-0K3204 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 07 60 $80.00 $213.91 $4800.00 02-21-2008 07-168004 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 07 60 $260.00 $695.22 $15600.00 02-21-2008 07-168004 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 07 60 $250.00 $668.48 $15000.00 02-21-2008 07-168004 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 07 60 $75.00 $200.54 $4500.00 02-21-2008 07-168004 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 240 $110.00 $294.13 $26400.00 03-20-2008 11-2T0004 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 240 $40.00 $106.96 $9600.00 03-20-2008 11-2T0004 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 240 $100.00 $267.39 $24000.00 03-20-2008 11-2T0004 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 240 $65.00 $173.80 $15600.00 03-20-2008 11-2T0004 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 240 $25.00 $66.85 $6000.00 03-20-2008 11-2T0004 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 240 $50.00 $133.70 $12000.00 03-20-2008 11-2T0004 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 155 $350.00 $935.87 $54250.00 05-01-2008 11-2T0914 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 155 $33.00 $88.24 $5115.00 05-01-2008 11-2T0914 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 155 $100.00 $267.39 $15500.00 05-01-2008 11-2T0914 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 155 $220.00 $588.26 $34100.00 05-01-2008 11-2T0914 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 155 $58.00 $155.09 $8990.00 05-01-2008 11-2T0914 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 155 $115.00 $307.50 $17825.00 05-01-2008 11-2T0914 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 155 $100.00 $267.39 $15500.00 05-01-2008 11-2T0914 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 495 $45.00 $120.33 $22275.00 07-10-2008 11-2T0924 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 495 $178.00 $475.96 $88110.00 07-10-2008 11-2T0924 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 11 495 $95.00 $254.02 $47025.00 07-10-2008 11-2T0924 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $383.50 $1025.44 $29146.00 08-19-2008 04-253794 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $70.00 $187.17 $5320.00 08-19-2008 04-253794 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $100.00 $267.39 $7600.00 08-19-2008 04-253794 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $100.00 $267.39 $7600.00 08-19-2008 04-253794 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $120.00 $320.87 $9120.00 08-19-2008 04-253794 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $95.00 $254.02 $7220.00 08-19-2008 04-253794 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $300.00 $802.17 $22800.00 08-19-2008 04-253794 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $150.00 $401.09 $11400.00 08-19-2008 04-253794 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $293.00 $783.45 $22268.00 08-19-2008 04-253794 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 76 $100.00 $267.39 $7600.00 08-19-2008 04-253794 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 185 $70.00 $187.17 $12950.00 08-19-2008 04-3S7704 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 185 $103.00 $275.41 $19055.00 08-19-2008 04-3S7704 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 185 $117.00 $312.85 $21645.00 08-19-2008 04-3S7704 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 185 $250.00 $668.48 $46250.00 08-19-2008 04-3S7704 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 185 $111.86 $299.10 $20694.10 08-19-2008 04-3S7704 5 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 185 $135.00 $360.98 $24975.00 08-19-2008 04-3S7704 6 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 185 $465.00 $1243.37 $86025.00 08-19-2008 04-3S7704 7 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 185 $500.00 $1336.95 $92500.00 08-19-2008 04-3S7704 8 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $12.50 $33.42 $11750.00 09-23-2008 05-485624 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $103.10 $275.68 $96914.00 09-23-2008 05-485624 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $50.00 $133.70 $47000.00 09-23-2008 05-485624 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $21.00 $56.15 $19740.00 09-23-2008 05-485624 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $69.50 $185.84 $65330.00 09-23-2008 05-485624 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $44.00 $117.65 $41360.00 09-23-2008 05-485624 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $35.00 $93.59 $32900.00 09-23-2008 05-485624 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $60.00 $160.43 $56400.00 09-23-2008 05-485624 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 940 $245.22 $655.70 $230506.80 09-23-2008 05-485624 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $300.00 $802.17 $4800.00 10-28-2008 02-1C1604 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $270.00 $721.95 $4320.00 10-28-2008 02-1C1604 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $450.00 $1203.26 $7200.00 10-28-2008 02-1C1604 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $90.00 $240.65 $1440.00 10-28-2008 02-1C1604 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $97.00 $259.37 $1552.00 10-28-2008 02-1C1604 5 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $200.00 $534.78 $3200.00 10-28-2008 02-1C1604 6 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $185.00 $494.67 $2960.00 10-28-2008 02-1C1604 7 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $182.00 $486.65 $2912.00 10-28-2008 02-1C1604 8 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $440.00 $1176.52 $7040.00 10-28-2008 02-1C1604 9 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $300.00 $802.17 $4800.00 10-28-2008 02-1C1604 10 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $100.00 $267.39 $1600.00 10-28-2008 02-1C1604 11 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 16 $200.00 $534.78 $3200.00 10-28-2008 02-1C1604 12 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 53 $297.00 $794.15 $15741.00 11-13-2008 08-472304 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 53 $75.00 $200.54 $3975.00 11-13-2008 08-472304 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 53 $105.00 $280.76 $5565.00 11-13-2008 08-472304 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 53 $288.00 $770.08 $15264.00 11-13-2008 08-472304 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 53 $76.00 $203.22 $4028.00 11-13-2008 08-472304 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 53 $80.00 $213.91 $4240.00 11-13-2008 08-472304 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 08 53 $200.00 $534.78 $10600.00 11-13-2008 08-472304 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $40.00 $106.96 $42000.00 11-14-2008 04-448804 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $60.00 $160.43 $63000.00 11-14-2008 04-448804 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $70.00 $187.17 $73500.00 11-14-2008 04-448804 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $40.00 $106.96 $42000.00 11-14-2008 04-448804 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $25.00 $66.85 $26250.00 11-14-2008 04-448804 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $25.00 $66.85 $26250.00 11-14-2008 04-448804 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $100.00 $267.39 $105000.00 11-14-2008 04-448804 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $56.00 $149.74 $58800.00 11-14-2008 04-448804 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $50.00 $133.70 $52500.00 11-14-2008 04-448804 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $30.00 $80.22 $31500.00 11-14-2008 04-448804 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1050 $200.00 $534.78 $210000.00 11-14-2008 04-448804 11 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $175.00 $467.93 $167125.00 12-10-2008 04-4A5204 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $45.00 $120.33 $42975.00 12-10-2008 04-4A5204 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $50.00 $133.70 $47750.00 12-10-2008 04-4A5204 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $10.00 $26.74 $9550.00 12-10-2008 04-4A5204 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $20.25 $54.15 $19338.75 12-10-2008 04-4A5204 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $160.00 $427.82 $152800.00 12-10-2008 04-4A5204 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $48.00 $128.35 $45840.00 12-10-2008 04-4A5204 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $24.00 $64.17 $22920.00 12-10-2008 04-4A5204 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $38.00 $101.61 $36290.00 12-10-2008 04-4A5204 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $75.00 $200.54 $71625.00 12-10-2008 04-4A5204 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $75.00 $200.54 $71625.00 12-10-2008 04-4A5204 11 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 955 $100.00 $267.39 $95500.00 12-10-2008 04-4A5204 12 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 156 $26.50 $84.41 $4134.00 03-24-2009 02-3C0804 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 156 $30.00 $95.56 $4680.00 03-24-2009 02-3C0804 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 156 $180.00 $573.38 $28080.00 03-24-2009 02-3C0804 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 156 $120.00 $382.25 $18720.00 03-24-2009 02-3C0804 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 156 $49.00 $156.09 $7644.00 03-24-2009 02-3C0804 5 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 156 $180.00 $573.38 $28080.00 03-24-2009 02-3C0804 6 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 156 $16.92 $53.90 $2639.52 03-24-2009 02-3C0804 7 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 156 $75.00 $238.91 $11700.00 03-24-2009 02-3C0804 8 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 154 $150.00 $477.82 $23100.00 07-29-2009 04-165424 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 154 $75.00 $238.91 $11550.00 07-29-2009 04-165424 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 154 $48.00 $152.90 $7392.00 07-29-2009 04-165424 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 154 $500.00 $1592.72 $77000.00 07-29-2009 04-165424 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 154 $275.00 $875.99 $42350.00 07-29-2009 04-165424 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 154 $150.00 $477.82 $23100.00 07-29-2009 04-165424 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 154 $100.00 $318.54 $15400.00 07-29-2009 04-165424 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 154 $100.00 $318.54 $15400.00 07-29-2009 04-165424 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $17.00 $54.15 $138465.00 07-30-2009 12-0G0404 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $16.00 $50.97 $130320.00 07-30-2009 12-0G0404 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $25.00 $79.64 $203625.00 07-30-2009 12-0G0404 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $85.00 $270.76 $692325.00 07-30-2009 12-0G0404 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $9.00 $28.67 $73305.00 07-30-2009 12-0G0404 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $13.00 $41.41 $105885.00 07-30-2009 12-0G0404 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $75.00 $238.91 $610875.00 07-30-2009 12-0G0404 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $28.00 $89.19 $228060.00 07-30-2009 12-0G0404 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 8145 $50.00 $159.27 $407250.00 07-30-2009 12-0G0404 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1630 $26.00 $82.82 $42380.00 09-29-2009 04-294914 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1630 $75.00 $238.91 $122250.00 09-29-2009 04-294914 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1630 $55.00 $175.20 $89650.00 09-29-2009 04-294914 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 1630 $96.00 $305.80 $156480.00 09-29-2009 04-294914 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $30.00 $95.56 $129900.00 10-06-2009 04-263724 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $30.00 $95.56 $129900.00 10-06-2009 04-263724 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $21.00 $66.89 $90930.00 10-06-2009 04-263724 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $21.00 $66.89 $90930.00 10-06-2009 04-263724 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $17.00 $54.15 $73610.00 10-06-2009 04-263724 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $20.00 $63.71 $86600.00 10-06-2009 04-263724 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $34.90 $111.17 $151117.00 10-06-2009 04-263724 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $33.00 $105.12 $142890.00 10-06-2009 04-263724 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 4330 $40.00 $127.42 $173200.00 10-06-2009 04-263724 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $22.50 $71.67 $64710.00 11-10-2009 04-283814 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $23.00 $73.27 $66148.00 11-10-2009 04-283814 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $26.55 $84.57 $76357.80 11-10-2009 04-283814 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $5.00 $15.93 $14380.00 11-10-2009 04-283814 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $8.00 $25.48 $23008.00 11-10-2009 04-283814 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $20.00 $63.71 $57520.00 11-10-2009 04-283814 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $30.00 $95.56 $86280.00 11-10-2009 04-283814 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $32.00 $101.93 $92032.00 11-10-2009 04-283814 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $20.00 $63.71 $57520.00 11-10-2009 04-283814 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $45.00 $143.34 $129420.00 11-10-2009 04-283814 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $36.00 $114.68 $103536.00 11-10-2009 04-283814 11 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $20.00 $63.71 $57520.00 11-10-2009 04-283814 12 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $22.00 $70.08 $63272.00 11-10-2009 04-283814 13 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 04 2876 $140.00 $445.96 $402640.00 11-10-2009 04-283814 14 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $30.00 $95.56 $80940.00 10-05-2010 04-2285C4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $10.00 $31.85 $26980.00 10-05-2010 04-2285C4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $19.00 $60.52 $51262.00 10-05-2010 04-2285C4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $18.00 $57.34 $48564.00 10-05-2010 04-2285C4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $25.00 $79.64 $67450.00 10-05-2010 04-2285C4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $14.00 $44.60 $37772.00 10-05-2010 04-2285C4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $28.00 $89.19 $75544.00 10-05-2010 04-2285C4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $13.00 $41.41 $35074.00 10-05-2010 04-2285C4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $20.00 $63.71 $53960.00 10-05-2010 04-2285C4 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $30.00 $95.56 $80940.00 10-05-2010 04-2285C4 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2698 $20.00 $63.71 $53960.00 10-05-2010 04-2285C4 11 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 475 $120.00 $382.25 $57000.00 11-30-2010 05-0161E4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 475 $23.00 $73.27 $10925.00 11-30-2010 05-0161E4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 475 $100.00 $318.54 $47500.00 11-30-2010 05-0161E4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 475 $70.00 $222.98 $33250.00 11-30-2010 05-0161E4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 475 $100.00 $318.54 $47500.00 11-30-2010 05-0161E4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 475 $46.00 $146.53 $21850.00 11-30-2010 05-0161E4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) M3 05 475 $160.00 $509.67 $76000.00 11-30-2010 05-0161E4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 242 $57.50 $163.28 $13915.00 08-16-2011 02-2E2004 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 242 $55.00 $156.19 $13310.00 08-16-2011 02-2E2004 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 242 $75.00 $212.98 $18150.00 08-16-2011 02-2E2004 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 242 $172.00 $488.43 $41624.00 08-16-2011 02-2E2004 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $25.00 $70.99 $61250.00 09-08-2011 07-2332A4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $50.00 $141.99 $122500.00 09-08-2011 07-2332A4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $25.00 $70.99 $61250.00 09-08-2011 07-2332A4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $25.00 $70.99 $61250.00 09-08-2011 07-2332A4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $65.00 $184.58 $159250.00 09-08-2011 07-2332A4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $26.00 $73.83 $63700.00 09-08-2011 07-2332A4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $25.00 $70.99 $61250.00 09-08-2011 07-2332A4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $78.80 $223.77 $193060.00 09-08-2011 07-2332A4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $25.00 $70.99 $61250.00 09-08-2011 07-2332A4 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $70.00 $198.78 $171500.00 09-08-2011 07-2332A4 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 2450 $16.00 $45.44 $39200.00 09-08-2011 07-2332A4 11 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $25.00 $70.99 $22500.00 09-14-2011 04-2285E4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $16.00 $45.44 $14400.00 09-14-2011 04-2285E4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $50.00 $141.99 $45000.00 09-14-2011 04-2285E4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $24.00 $68.15 $21600.00 09-14-2011 04-2285E4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $11.00 $31.24 $9900.00 09-14-2011 04-2285E4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $35.00 $99.39 $31500.00 09-14-2011 04-2285E4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $60.00 $170.38 $54000.00 09-14-2011 04-2285E4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $60.00 $170.38 $54000.00 09-14-2011 04-2285E4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 900 $24.00 $68.15 $21600.00 09-14-2011 04-2285E4 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $26.00 $73.83 $75140.00 09-27-2011 04-4A07U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $145.00 $411.76 $419050.00 09-27-2011 04-4A07U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $12.00 $34.08 $34680.00 09-27-2011 04-4A07U4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $31.15 $88.46 $90023.50 09-27-2011 04-4A07U4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $20.00 $56.79 $57800.00 09-27-2011 04-4A07U4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $70.00 $198.78 $202300.00 09-27-2011 04-4A07U4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $108.00 $306.69 $312120.00 09-27-2011 04-4A07U4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $30.00 $85.19 $86700.00 09-27-2011 04-4A07U4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $44.00 $124.95 $127160.00 09-27-2011 04-4A07U4 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $100.00 $283.97 $289000.00 09-27-2011 04-4A07U4 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $65.00 $184.58 $187850.00 09-27-2011 04-4A07U4 11 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 435 $44.00 $124.95 $19140.00 10-25-2011 04-298304 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 435 $30.00 $85.19 $13050.00 10-25-2011 04-298304 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 435 $70.00 $198.78 $30450.00 10-25-2011 04-298304 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 435 $35.00 $99.39 $15225.00 10-25-2011 04-298304 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 435 $38.00 $107.91 $16530.00 10-25-2011 04-298304 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 435 $30.00 $85.19 $13050.00 10-25-2011 04-298304 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3410 $25.00 $70.99 $85250.00 12-06-2011 04-264134 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3410 $13.00 $36.92 $44330.00 12-06-2011 04-264134 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3410 $18.00 $51.12 $61380.00 12-06-2011 04-264134 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3410 $15.00 $42.60 $51150.00 12-06-2011 04-264134 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3410 $15.50 $44.02 $52855.00 12-06-2011 04-264134 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3410 $15.00 $42.60 $51150.00 12-06-2011 04-264134 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3410 $35.00 $99.39 $119350.00 12-06-2011 04-264134 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4743 $90.00 $255.58 $426870.00 12-08-2011 08-448404 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4743 $25.00 $70.99 $118575.00 12-08-2011 08-448404 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4743 $20.00 $56.79 $94860.00 12-08-2011 08-448404 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4743 $9.00 $25.56 $42687.00 12-08-2011 08-448404 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4743 $20.00 $56.79 $94860.00 12-08-2011 08-448404 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4743 $15.00 $42.60 $71145.00 12-08-2011 08-448404 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4743 $32.00 $90.87 $151776.00 12-08-2011 08-448404 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 30610 $14.00 $39.76 $428540.00 12-13-2011 04-264144 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 30610 $10.00 $28.40 $306100.00 12-13-2011 04-264144 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 30610 $17.00 $48.28 $520370.00 12-13-2011 04-264144 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 30610 $4.00 $11.36 $122440.00 12-13-2011 04-264144 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 30610 $28.00 $79.51 $857080.00 12-13-2011 04-264144 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 30610 $19.00 $53.95 $581590.00 12-13-2011 04-264144 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 30610 $30.00 $85.19 $918300.00 12-13-2011 04-264144 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $50.00 $143.94 $50900.00 02-22-2012 04-297614 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $20.00 $57.58 $20360.00 02-22-2012 04-297614 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $11.00 $31.67 $11198.00 02-22-2012 04-297614 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $35.00 $100.76 $35630.00 02-22-2012 04-297614 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $12.00 $34.55 $12216.00 02-22-2012 04-297614 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $48.00 $138.18 $48864.00 02-22-2012 04-297614 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $25.00 $71.97 $25450.00 02-22-2012 04-297614 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $43.00 $123.79 $43774.00 02-22-2012 04-297614 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $210.00 $604.54 $213780.00 02-22-2012 04-297614 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $14.00 $40.30 $14252.00 02-22-2012 04-297614 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $27.00 $77.73 $27486.00 02-22-2012 04-297614 11 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1018 $110.00 $316.67 $111980.00 02-22-2012 04-297614 12 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $20.00 $54.98 $57800.00 04-25-2012 04-4A07U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $26.00 $71.48 $75140.00 04-25-2012 04-4A07U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $12.00 $32.99 $34680.00 04-25-2012 04-4A07U4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $200.00 $549.83 $578000.00 04-25-2012 04-4A07U4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $29.30 $80.55 $84677.00 04-25-2012 04-4A07U4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $21.00 $57.73 $60690.00 04-25-2012 04-4A07U4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 2890 $23.00 $63.23 $66470.00 04-25-2012 04-4A07U4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 6090 $25.00 $80.87 $152250.00 08-24-2012 05-315804 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 6090 $50.00 $161.73 $304500.00 08-24-2012 05-315804 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 6090 $15.00 $48.52 $91350.00 08-24-2012 05-315804 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 6090 $150.00 $485.20 $913500.00 08-24-2012 05-315804 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 6090 $15.00 $48.52 $91350.00 08-24-2012 05-315804 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 561 $25.00 $80.87 $14025.00 08-29-2012 04-2908E4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 561 $40.80 $131.97 $22888.80 08-29-2012 04-2908E4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 561 $45.00 $145.56 $25245.00 08-29-2012 04-2908E4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 561 $70.00 $226.43 $39270.00 08-29-2012 04-2908E4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 561 $40.00 $129.39 $22440.00 08-29-2012 04-2908E4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 561 $30.00 $97.04 $16830.00 08-29-2012 04-2908E4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 561 $50.00 $161.73 $28050.00 08-29-2012 04-2908E4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 561 $100.00 $323.47 $56100.00 08-29-2012 04-2908E4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 420 $55.00 $177.91 $23100.00 09-05-2012 04-2640U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 420 $17.00 $54.99 $7140.00 09-05-2012 04-2640U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 420 $20.00 $64.69 $8400.00 09-05-2012 04-2640U4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 420 $31.00 $100.27 $13020.00 09-05-2012 04-2640U4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 420 $60.00 $194.08 $25200.00 09-05-2012 04-2640U4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 420 $75.00 $242.60 $31500.00 09-05-2012 04-2640U4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 4129 $20.00 $64.69 $82580.00 09-19-2012 04-2908C4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 4129 $20.00 $64.69 $82580.00 09-19-2012 04-2908C4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 4129 $21.70 $70.19 $89599.30 09-19-2012 04-2908C4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 4129 $30.00 $97.04 $123870.00 09-19-2012 04-2908C4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 4129 $14.00 $45.29 $57806.00 09-19-2012 04-2908C4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 4129 $23.00 $74.40 $94967.00 09-19-2012 04-2908C4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 4129 $15.00 $48.52 $61935.00 09-19-2012 04-2908C4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 4129 $60.00 $194.08 $247740.00 09-19-2012 04-2908C4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1455 $25.00 $62.30 $36375.00 10-05-2012 04-2908V4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1455 $25.00 $62.30 $36375.00 10-05-2012 04-2908V4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1455 $26.20 $65.29 $38121.00 10-05-2012 04-2908V4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1455 $23.00 $57.32 $33465.00 10-05-2012 04-2908V4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1455 $18.00 $44.86 $26190.00 10-05-2012 04-2908V4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1455 $20.00 $49.84 $29100.00 10-05-2012 04-2908V4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 46 $300.00 $747.60 $13800.00 10-09-2012 04-4S0204 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 46 $80.00 $199.36 $3680.00 10-09-2012 04-4S0204 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 46 $200.00 $498.40 $9200.00 10-09-2012 04-4S0204 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 46 $125.00 $311.50 $5750.00 10-09-2012 04-4S0204 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4541 $20.00 $49.84 $90820.00 10-11-2012 08-0M94U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4541 $20.00 $49.84 $90820.00 10-11-2012 08-0M94U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4541 $21.00 $52.33 $95361.00 10-11-2012 08-0M94U4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4541 $35.00 $87.22 $158935.00 10-11-2012 08-0M94U4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 4541 $7.00 $17.44 $31787.00 10-11-2012 08-0M94U4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1008 $50.00 $124.60 $50400.00 11-28-2012 04-2285H4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1008 $25.00 $62.30 $25200.00 11-28-2012 04-2285H4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1008 $30.00 $74.76 $30240.00 11-28-2012 04-2285H4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1008 $60.00 $149.52 $60480.00 11-28-2012 04-2285H4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1008 $50.00 $124.60 $50400.00 11-28-2012 04-2285H4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1008 $35.00 $87.22 $35280.00 11-28-2012 04-2285H4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1008 $50.00 $124.60 $50400.00 11-28-2012 04-2285H4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1008 $132.00 $328.94 $133056.00 11-28-2012 04-2285H4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3323 $24.00 $50.24 $79752.00 01-15-2013 04-2A4404 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3323 $13.00 $27.21 $43199.00 01-15-2013 04-2A4404 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3323 $175.00 $366.33 $581525.00 01-15-2013 04-2A4404 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3323 $18.00 $37.68 $59814.00 01-15-2013 04-2A4404 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3323 $22.00 $46.05 $73106.00 01-15-2013 04-2A4404 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3323 $25.00 $52.33 $83075.00 01-15-2013 04-2A4404 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3323 $35.00 $73.27 $116305.00 01-15-2013 04-2A4404 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 3323 $20.00 $41.87 $66460.00 01-15-2013 04-2A4404 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $35.00 $73.27 $29785.00 02-07-2013 07-3X1804 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $2.00 $4.19 $1702.00 02-07-2013 07-3X1804 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $42.00 $87.92 $35742.00 02-07-2013 07-3X1804 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $45.00 $94.20 $38295.00 02-07-2013 07-3X1804 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $63.00 $131.88 $53613.00 02-07-2013 07-3X1804 5 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $15.00 $31.40 $12765.00 02-07-2013 07-3X1804 6 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $30.00 $62.80 $25530.00 02-07-2013 07-3X1804 7 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $45.00 $94.20 $38295.00 02-07-2013 07-3X1804 8 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 07 851 $53.00 $110.94 $45103.00 02-07-2013 07-3X1804 9 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 890 $33.00 $58.12 $29370.00 04-30-2013 02-2E3504 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 890 $37.00 $65.16 $32930.00 04-30-2013 02-2E3504 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 890 $160.00 $281.79 $142400.00 04-30-2013 02-2E3504 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 02 890 $50.00 $88.06 $44500.00 04-30-2013 02-2E3504 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $26.00 $83.73 $19864.00 08-08-2013 12-0C5604 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $90.00 $289.84 $68760.00 08-08-2013 12-0C5604 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $70.00 $225.43 $53480.00 08-08-2013 12-0C5604 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $40.00 $128.82 $30560.00 08-08-2013 12-0C5604 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $18.00 $57.97 $13752.00 08-08-2013 12-0C5604 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $26.00 $83.73 $19864.00 08-08-2013 12-0C5604 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $34.00 $109.49 $25976.00 08-08-2013 12-0C5604 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $55.00 $177.12 $42020.00 08-08-2013 12-0C5604 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $200.00 $644.09 $152800.00 08-08-2013 12-0C5604 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 764 $50.00 $161.02 $38200.00 08-08-2013 12-0C5604 10 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 11 6570 $65.00 $209.33 $427050.00 09-12-2013 11-0223U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 11 6570 $30.00 $96.61 $197100.00 09-12-2013 11-0223U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 11 6570 $15.50 $49.92 $101835.00 09-12-2013 11-0223U4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 11 6570 $80.00 $257.64 $525600.00 09-12-2013 11-0223U4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 11 6570 $35.00 $112.72 $229950.00 09-12-2013 11-0223U4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 11 6570 $17.30 $55.71 $113661.00 09-12-2013 11-0223U4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 01 230 $125.00 $402.55 $28750.00 09-17-2013 01-450904 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 01 230 $34.00 $109.49 $7820.00 09-17-2013 01-450904 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 01 230 $250.00 $805.11 $57500.00 09-17-2013 01-450904 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 01 230 $90.00 $289.84 $20700.00 09-17-2013 01-450904 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 01 230 $1000.00 $3220.44 $230000.00 09-17-2013 01-450904 5 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 735 $110.00 $354.25 $80850.00 09-24-2013 04-2A4304 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 735 $44.00 $141.70 $32340.00 09-24-2013 04-2A4304 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 735 $47.00 $151.36 $34545.00 09-24-2013 04-2A4304 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 735 $90.00 $289.84 $66150.00 09-24-2013 04-2A4304 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 735 $100.00 $322.04 $73500.00 09-24-2013 04-2A4304 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 735 $84.00 $270.52 $61740.00 09-24-2013 04-2A4304 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 735 $70.00 $225.43 $51450.00 09-24-2013 04-2A4304 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 1591 $70.00 $155.65 $111370.00 10-31-2013 12-0F96E4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 1591 $80.00 $177.88 $127280.00 10-31-2013 12-0F96E4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 1591 $20.00 $44.47 $31820.00 10-31-2013 12-0F96E4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 1591 $135.00 $300.18 $214785.00 10-31-2013 12-0F96E4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 1591 $30.00 $66.71 $47730.00 10-31-2013 12-0F96E4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 12 1591 $75.00 $166.76 $119325.00 10-31-2013 12-0F96E4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 686 $232.00 $413.51 $159152.00 02-12-2014 05-1C1804 1 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 686 $180.00 $320.83 $123480.00 02-12-2014 05-1C1804 2 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 686 $62.00 $110.51 $42532.00 02-12-2014 05-1C1804 3 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 686 $100.00 $178.24 $68600.00 02-12-2014 05-1C1804 4 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 686 $175.00 $311.92 $120050.00 02-12-2014 05-1C1804 5 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 05 686 $91.00 $162.20 $62426.00 02-12-2014 05-1C1804 6 M  
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 7713 $111.00 $255.54 $856143.00 04-29-2014 04-2A2504 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 7713 $40.00 $92.08 $308520.00 04-29-2014 04-2A2504 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 7713 $13.00 $29.93 $100269.00 04-29-2014 04-2A2504 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 7713 $15.00 $34.53 $115695.00 04-29-2014 04-2A2504 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1267 $32.00 $71.14 $40544.00 07-08-2014 04-152724 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1267 $40.00 $88.93 $50680.00 07-08-2014 04-152724 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1267 $75.00 $166.74 $95025.00 07-08-2014 04-152724 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1267 $40.00 $88.93 $50680.00 07-08-2014 04-152724 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1267 $100.00 $222.32 $126700.00 07-08-2014 04-152724 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1267 $60.00 $133.39 $76020.00 07-08-2014 04-152724 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 04 1267 $55.00 $122.28 $69685.00 07-08-2014 04-152724 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $27.00 $60.03 $20898.00 07-24-2014 08-3401U4 1 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $25.00 $55.58 $19350.00 07-24-2014 08-3401U4 2 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $40.00 $88.93 $30960.00 07-24-2014 08-3401U4 3 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $47.00 $104.49 $36378.00 07-24-2014 08-3401U4 4 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $20.00 $44.46 $15480.00 07-24-2014 08-3401U4 5 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $40.00 $88.93 $30960.00 07-24-2014 08-3401U4 6 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $20.00 $44.46 $15480.00 07-24-2014 08-3401U4 7 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $50.00 $111.16 $38700.00 07-24-2014 08-3401U4 8 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $70.00 $155.62 $54180.00 07-24-2014 08-3401U4 9 M TRO
192055 - STRUCTURE EXCAVATION (SOIL NAIL WALL) CY 08 774 $215.00 $477.98 $166410.00 07-24-2014 08-3401U4 10 M TRO
MORE THAN 500 RESULTS RETURNED. ONLY 500 ROWS SHOWN.
SUMMARY Unmodified Adjusted    
Average Price/Unit: $ Avg No. Units
Std Dev. (of Unit Price): ±$ Rows Selected
Weighted Avg.: $ Rows Returned
Minimum Price/Unit: $    
Maximum Price/Unit: $    

| Back | New Search |

PARAMETERS: Item = 192055; District=All; Year=All; Convert=No; Bidders=All Bidders
TIMESTAMP: 11/13/2026 05:27:01
CURRENT 12-MO INDEX (CHCCI (2020 Base)): 146.53